Waterproofing compliance under the Design and Building Practitioners Act
Most owners corporations reach this question the same way. A building report flags water ingress, a balcony or podium slab starts leaking into the units below, or an insurer or building manager raises the Design and Building Practitioners Act as a condition of approving the remedial works. The committee then needs two answers quickly: whether the Act applies to this particular job, and who they are allowed to engage to do it.
This page sets out what the Act requires for waterproofing on Class 2 buildings, the one narrow exemption and its three conditions, who is permitted to prepare and lodge each document, and what happens when the sequence is not followed. If you are looking for the waterproofing work itself rather than the compliance pathway, our waterproofing services page covers the systems we install and the applications we work across.
Does the Act apply to your building
Waterproofing is a regulated building element under the Act, alongside elements such as structure, fire safety systems and the building enclosure. The scheme applies to Class 2 buildings, which are residential apartment buildings, and it has applied to them since 1 July 2021. Mixed-use buildings are captured where they contain Class 2 parts, so a retail ground floor with apartments above it sits inside the scheme. Class 3 and Class 9c buildings are dealt with separately in the guidance, and the obligations should not be assumed to be identical across classes.
If your building is a Class 2 strata scheme and the works involve waterproofing, the starting assumption is that the Act applies. The question worth spending time on is whether the one exemption releases you, and for most strata buildings it does not.
The one exemption, and why it almost never applies to a strata building
The Design and Building Practitioners Regulation 2021 excludes waterproofing from building work at clause 13(1)(b), and the exclusion applies “but only if” three conditions are all satisfied together:
- the work is carried out as a result of alterations to a bathroom, kitchen, laundry or toilet, and
- the alterations are carried out as exempt development, and
- the work, including the agreement to carry out the work, relates only to a single dwelling.
All three have to be true at once. Fail any one of them and the exemption is gone.
For a multi-unit strata building that is a high bar to clear. Remedial waterproofing to common property fails the third condition immediately. Works that cross more than one lot fail it too. A balcony, podium, rooftop, planter box or retaining wall is not an alteration to a bathroom, kitchen, laundry or toilet, so it fails the first condition regardless of anything else. And where a development application or a complying development certificate is required, the second condition falls away.
Exempt development and the Act are decided separately, which is the point most often missed. ACRA states it plainly in its own waterproofing fact sheet: “if the works are not subject to a DA or CDC, but do involve waterproofing across multiple units, the DBPA applies even if the remedial works are an exempt development”. NSW Fair Trading makes the same point in its guidance on remedial building work, describing waterproofing as an example of exempt development that is not always excluded from being building work under the Act.
The sequence of declarations, and who lodges what
The order matters more than the paperwork, because the consequence of getting it wrong does not appear until the end of the project.
Before work starts. A registered design practitioner prepares a regulated design for the waterproofing and makes a design compliance declaration confirming the design complies with the Building Code of Australia. For remedial work on a Class 2 building, that design is lodged as a Construction Issued Regulated Design on the NSW Planning Portal, and it is the registered building practitioner or appropriate practitioner who lodges it, before construction starts.
During the work. The registered building practitioner must build in accordance with the declared design. Departing from it without a varied design and a fresh declaration breaks the chain.
At completion. The registered building practitioner lodges a building compliance declaration confirming the work is consistent with the declared design and compliant with the Building Code of Australia.
The consequence. Many remedial jobs do not need an occupation certificate, but where one is needed, a certifier cannot issue it until all compliance declarations have been lodged. Either way, the declarations are part of the job, and unwinding a missed step after the fact takes longer and costs more than sequencing it correctly at the start, which is why they belong in the scope and the budget from day one rather than being discovered at handover.
Who is allowed to prepare a waterproofing design
This is where strata committees most often get stuck, because there is no waterproofing class of design practitioner. NSW registers design practitioners in classes including architectural, building design, structural engineering, civil engineering, facade, fire safety engineering, geotechnical engineering, mechanical engineering, electrical engineering, drainage and vertical transportation. Waterproofing is not among them.
In practice the regulated waterproofing design is prepared by a practitioner registered in a class that covers the element, commonly architectural, building design, structural, civil or facade, and that practitioner is frequently supported by a specialised waterproofing consultant who brings the membrane and detailing expertise. The consultant does not replace the registered practitioner, and the declaration still has to come from someone holding the right registration.
If a contractor offers to handle the design themselves without naming the registered design practitioner and their class, that is the moment to ask, because the declaration is only as good as the registration behind it. You can check any practitioner’s registration on the NSW Fair Trading register before you engage them.
AS 3740:2021 and the standard the work has to meet
The operative Australian Standard for internal wet area waterproofing is AS 3740:2021. A regulated design declared against the Building Code of Australia has to reflect the current version, so if a scope of works cites AS 3740 without naming a year, it is worth asking which version the contractor has priced to, because the answer changes what gets built and what the design practitioner can declare.
How BiM Remedial Sydney manages waterproofing compliance
BiM Remedial Sydney is a fully registered Building Practitioner (BUP0002318) and a licensed remedial building contractor under NSW Builder Licence 198846C, which means the same team that carries out the waterproofing is the team that lodges the declarations around it. We are an ACRA member, a Master Builders Association member since 2015, and certified to ISO 9001, ISO 14001 and ISO 45001, with nearly 30 years in remedial building work, more than $80M in completed remedial projects and over 1,000 clients served across Sydney.
We identify the work triggers that bring your project inside the Act
We start with inspection and diagnosis, because the scope of the regulated work depends on what is actually failing rather than on what is visible from the balcony door, and because whether the Act applies turns on details like how many lots the work crosses and whether common property is involved.
We coordinate the regulated design and the design compliance declaration
We scope the regulated waterproofing work and coordinate with a registered design practitioner in the appropriate class, supported by a specialised waterproofing consultant where the detailing calls for it, so the regulated design and its design compliance declaration exist before work begins rather than after.
We lodge the Construction Issued Regulated Design and the building compliance declaration
As the registered building practitioner we lodge the Construction Issued Regulated Design on the NSW Planning Portal before construction starts, build in accordance with the declared design, and lodge the building compliance declaration at completion. We retain the records, because registered practitioners must keep regulated designs and compliance declarations for a minimum of ten years.
What usually triggers the obligation on a Class 2 building
The scenarios that bring a strata scheme inside the Act are consistent, and recognising yours early saves the most money.
Balcony membranes are the most common. Failure usually shows up at the door threshold, where the upturn is too low or the falls send water back toward the building rather than to the outlet, and the first sign is staining on the ceiling of the unit below. Because a balcony is not an alteration to a bathroom, kitchen, laundry or toilet, that work is captured whatever else is true of it.
Podium slabs over basement car parks are the most expensive, because the membrane sits under landscaping, paving or planters, and the cost of the remedy is driven by what has to come off before the membrane can be reached. Planter boxes fail in the same way and for the same reason.
Rooftops and their penetrations come next, usually where plant has been added or replaced over the years and the flashings around the new penetrations were never detailed properly.
Internal wet areas are the smallest of the four, and the one case where the clause 13 exemption can genuinely apply, but only for a single dwelling and only where the other two conditions are also met.
In each of these, the compliance question and the diagnostic question are the same question. The scope of the regulated work depends on what is actually failing, which is why a proper investigation comes before a price rather than after it.
What we will and will not tell you about compliance
We will tell you when a scope does not need the full regulated design pathway, and we will tell you when your building is not a fit for us. We do not issue waterproofing compliance certificates, because the Act does not create such a document, and any contractor offering one on their own letterhead is giving you something other than what the legislation requires. What the Act creates is the regulated design, the design compliance declaration and the building compliance declaration.
What to do next
If your building report has flagged waterproofing and you are not sure where you stand, the practical order is this. Get a specialised waterproofing consultant assessment so the defect is properly diagnosed before anyone prices a scope. Establish whether clause 13 releases you, which for a strata scheme usually means confirming that it does not. Then engage a registered building practitioner who will coordinate the regulated design with a practitioner in the right class and lodge the declarations in the right order. Our Design and Building Practitioners Act page sets out our registration and how we work under the scheme.
Waterproofing compliance NSW: frequently asked questions
Does the Act apply if our balcony waterproofing is exempt development?
Yes, in most cases. The clause 13(1)(b) exclusion only applies where all three of its conditions are met together, and balcony work fails the first condition because it is not an alteration to a bathroom, kitchen, laundry or toilet. Where works are not subject to a development application or a complying development certificate but involve waterproofing across multiple units, the Act applies even where the remedial works are exempt development.
Does the Act apply to a single apartment bathroom renovation?
That is the one case where the exemption can apply, but only if all three conditions in clause 13(1)(b) are satisfied together: the work results from alterations to a bathroom, kitchen, laundry or toilet, those alterations are carried out as exempt development, and the work relates only to a single dwelling. Once the work touches common property or a second lot, the exemption is gone.
Who does the DBP Act apply to?
It applies to registered design practitioners who prepare regulated designs, registered building practitioners who carry out the work and lodge building compliance declarations, and registered professional engineers. For an owners corporation, the practical answer is that the Act governs who you are allowed to engage, because a contractor who is not a registered building practitioner cannot lodge the building compliance declaration the Act requires.
Which class of design practitioner prepares a waterproofing design?
There is no waterproofing class. The regulated design is prepared by a practitioner registered in a class that covers the element, commonly architectural, building design, structural, civil or facade, often working alongside a specialised waterproofing consultant.
Is waterproofing considered structural?
Not in the load bearing sense, and the distinction does not change your obligations, because waterproofing is a regulated building element in its own right. Where a waterproofing failure has already caused concrete spalling or steel corrosion, the remedial scope usually becomes structural as well, and both elements then need to be covered by the design and the declarations.
What happens if a compliance declaration is not lodged before work commences?
The work proceeds without the documentation the scheme requires, and the gap usually surfaces at the end rather than the start. Where the job needs an occupation certificate, a certifier cannot issue it until all compliance declarations have been lodged. Where it does not, the declarations are still required, and putting them right after the fact takes longer and costs more than lodging them in sequence.
How long do compliance records have to be kept?
Registered practitioners must retain copies of all regulated designs and compliance declarations for a minimum of ten years.
Find out more - contact BiM Remedial Sydney today
If waterproofing has been flagged on your Class 2 or mixed-use building, we can carry out a compliance assessment: inspect the building, diagnose the defect, tell you whether clause 13 releases you, and set out which design instrument and which declarations your project needs before anything starts.
Call us today on 02 9938 1740 or email us at quotes@bimsydney.com.au.
More Services
- Concrete Spalling Repairs for Strata & Commercial Buildings Sydney
- Concrete Cancer Diagnosis & Structural Repair Sydney
- Concrete Driveway Services
- Commercial Fit-Outs
- Design and Building Practitioners Act
- Strata Services – Strata Agents
Speak to a registered building practitioner
Call BiM Remedial Sydney on 02 9938 1740, or email quotes@bimsydney.com.au to arrange a compliance assessment.
Last reviewed: September 2026.